Director RDD reviews status of MGNREGA, other schemes

Director RDD reviews status of MGNREGA, other schemes
Decrease Font Size Increase Font Size Text Size Print This Page

Stresses on achieving targets in full, no spillovers

ANANTNAG: Director, Rural Development (RDD) Kashmir, Tariq Ahmad Zargar Saturday visited Anantnag to review the progress of various flagship Rural Development schemes under implementation in the district.
Assistant Commissioner Development Anantnag, Assistant Commissioner Panchayat, Anantnag, SE (REW), Executive Engineer (REW) Anantnag, BDOs, AEEs and other officers attended the review meeting.
The status of various rural flagship schemes including MGNREGA, PMAY-G and 14th FCA besides progress of works taken up under the Capex Budget (CD & Pyt Sector) District Capex (DDC, BDC & PRI Grants) and construction of DDC/ BDC Offices, RGSA was reviewed in detail.
ACD Anantnag informed that Anantnag has achieved 98% target in respect of person days generated under MGNREGA. Against a target of 34.79 Lakh person days set for ending March 2022, 34.02 Lakh person days have already been generated till date. Moreover, MGNREGA Wages are being released in time among the MGNREGA Job Card Holders and till date Rs74.80 Crore have been paid under labour component besides 100% geo-tagging of assets and 99.61% Aadhaar Seeding of Job Card Holders is complete.
Similarly, out of the 8077 works taken up under MGNREGA, 3452 works have been completed while remaining are at final stages of execution. BDOs were instructed to complete the remaining works both physically as well as financially by or before March, 31, 2022.
Furthermore, under PMAY-G, against the approved target of 2315 units, 2131 housing units have been completed till date. The 1st installment in favor of all 2315 beneficiaries, 2nd installment in favor of 2311 and 3rd installment in favor of 2142 beneficiaries has been released. Additionally, under the Non SECC PMAY-G, out of the 3253 units target, 2074 have been sanctioned till date and 1st installment in favor of 700 beneficiaries has been released. “The sanctioning of remaining units and release of 1st installment in favor of beneficiaries is being expedited and the target will be achieved in full” ACD Anantnag said.
Under the Capex Budget CD & Pyt Sector, out of the 157 works taken-up for execution, 83 have been completed and remaining are at final stages of completion. Moreover, under Rural Connectivity, out of the 6 works taken up, 3 have been completed.
It was further informed that during the current financial year, one DDC Office at Anantnag and three BDC Offices at Shangus, Hiller and K Pora have been approved for construction.