KV News

DC Sgr inspects progress on ongoing development projects

Decrease Font Size Increase Font Size Text Size Print This Page

SRINAGAR: Deputy Commissioner (DC) Srinagar Mohammad Aijaz Asad Wednesday undertook a visit to Tengpora Bemina area to oversee the progress of works being carried out on several major developmental projects.

The projects  included Animal Birth Control and Anti Rabies Centre, SlaughterHouse Alochibagh, STP Tengpora and 150 MVA GIS Power Sub Station Alochibagh.

The DC was accompanied by Chief Planning Officer Srinagar, Mohammad Yaseen Lone, Joint Commissioner Works, SMC, Rajindra Singh, Executive Engineer, JKPCC and other concerned.

While reviewing the progress of work on Animal Birth Control Centre at Tengpora being constructed at a cost of Rs 1.43 crore with all the modern facilities, the DC was apprised that the Centre is having a capacity of conducting 60 sterilization surgeries in a day, besides will also house an Anti-Rabies Vaccination Centre,

The DC was informed that the project is near to completion and over 90 percent work on the Sterilization cum Vaccination Centre has been completed and the remaining work is going at a faster pace.

The DC asked the concerned Officers to expedite the works on Administrative block, Operation theatre, procurement surgical equipment with OT table, besides works for construction of walkways, greenspace and allied face lifting works.

At Alochi Bagh, the DC inspected the works on the proposed Modern Sheep Abattoir (Slaughter House) at a cost of Rs 24.52 crore.

At the site, the DC was given a detailed appraisal that the process for hiring a consultancy is in progress and accordingly work shall commence to establish a modern abattoir facility.

Similarly, the DC took stock of the work being executed on Alochi Bagh-Tengpora STP under construction at Rs 12.7 crore to strengthen the drainage/sewerage network system in the area.

Later, he DC inspected the ongoing work on Rs 8 crore 150 MVA GIS Power SubStation at Alochi Bagh which is nearing completion.

On the occasion, the DC asked the concerned to work in double shifts to complete the remaining part of the project to further improve the power supply in areas of Rajbagh, Padshahi Bagh, Alochi Bagh, Jawahar Nagar, Exhibition, Silk factory, Tengpora and other adjoining areas to be catered by the GIS substation.

 